Maria to Kristin Topside Project

Type of Contract Topside EPCI – Tie-in modifications

Client Statoil ASA

Start 2015

Finished 2017



Description

EPCI contract for modification of the Kristin process facilities to accommodate a subsea tie-back of the Maria development to Kristin platform through new subsea infrastructure.

The Maria wellstream will be tied back to Kristin SEMI through a dedicated flowline connected to the existing N-101 riser slot. The topside piping from this slot is currently connected to the existing Kristin production manifold.

The following new technical interfaces will be introduced to Kristin topside:

The following Topside building blocks defines the scope of work included:

Approximate contract value: 650 MNOK